LEED Construction & Demolition Waste Management Plan

For commercial builders and project managers, the LEED Construction & Demolition Waste Management Plan (C&D WMP) serves as a tool for balancing eco-friendly waste practices with construction needs. This guide explains what goes into a LEED C&D WMP, effective strategies, and how Fuzion can help streamline the process.

Understanding LEED and the Role of C&D Waste Management

LEED Overview

Leadership in Energy and Environmental Design (LEED) is a worldwide certification developed by the US Green Building Council (USGBC). It sets detailed standards for creating sustainable buildings through design, construction, and operation. Projects gain points in various areas and can reach one of four levels: Certified, Silver, Gold, or Platinum.

Within LEED, the Materials and Resources (MR) credit category emphasizes waste reduction, sustainable sourcing, and building life-cycle impact reduction. Credits MRc2.1 and MRc2.2 specifically target construction and demolition (C&D) waste management​​.

Purpose of C&D Waste Management Credits

These credits emphasize the importance of reducing the environmental impact of construction waste by diverting debris from landfills. A successful LEED C&D Waste Management Plan achieves the following:

  • Diverts Construction & Demolition Debris:
Diverts a minimum of 50% of non-hazardous C&D debris (v4.1) or 75% (v4) by promoting recycling and reuse practices​.
  • Promotes Material Reuse and Recycling: Encourages the reuse and recycling of materials to redirect them from disposal, thereby reducing demand for virgin materials and minimizing the project’s carbon footprint​​.
  • Establishes Diversion Goals:
Sets clear goals and defines five targeted materials to ensure valuable resources are repurposed, ultimately supporting circular economy principles​​. These targeted materials typically include concrete, metals, wood, masonry, and cardboard​​.

By providing a broader context for sustainable waste management, these credits guide construction projects in reducing their environmental impact and promote the responsible handling of valuable resources.

Changes in LEED v4.1

LEED v4.1 simplifies Construction Waste Management credits by reducing material stream targets and excluding demolition waste from the total calculation, making it easier for project teams to achieve higher diversion rates and streamline certification.

Simplified Material Stream Requirements

Reduced stream targets: 50% reduction using commingled recycling plus one stream, 75% reduction plus two streams.

Option 2 Improvements

Demolition waste exclusion and new waste thresholds: 7.5 lbs/sf (new construction), 2.5 lbs/sf (Core and Shell projects).

Enhanced Reporting Accuracy

Commingled facilities must provide project-specific diversion rates; visual inspection is no longer sufficient.

These changes make it more feasible for project teams to achieve higher diversion rates, improve waste management strategies, and earn valuable LEED credits.

LEED Construction & Demolition Waste Management Plan Requirements

Cleaning up metal waste from a jobsite.
Cleaning up metal waste from a jobsite.

Waste Diversion Goals

A LEED C&D WMP sets specific waste diversion goals to ensure compliance with MR credits:

  • LEED v4.1: Divert a minimum of 50% of C&D debris by identifying and targeting three material streams.
  • LEED v4: Divert at least 75% of C&D debris by identifying and targeting five material streams​​.

Key Plan Components

Identification of Waste Sources

Recognizing the primary sources of waste, including concrete, scrap metal, cardboard, timber, and more​​.

Example Materials and Estimated Diversion Rates

Targeted materials typically include concrete, metals, wood, masonry, and cardboard. Diversion rates vary per project, with concrete reaching up to 40%, metals up to 15%, and other materials like gypsum board and cardboard varying accordingly.

Exclusion of Non-Qualifying Materials

Excavated soil and land-clearing debris cannot count toward diversion credits​​.

Waste Stream Calculation

Different recycling protocols (e.g., commingled vs. separate bin) and their respective diversion requirements​​.

Recycling Protocols

Outline the method of recycling (commingled or separate bins) and set specific diversion rate targets for each material​​.

Tracking and Reporting

Prepare detailed documentation of each waste stream’s diversion and disposal rates. Reporting must be consistent with LEED credit requirements​.

Tagged/Curated

A Quick Guide to Sustainable Resource Management Practices